The installation was carried out under the guidance of representatives of M&L Engineering GmbH (Germany) and VZDUCHOTORG (Slovakia). For the installation of equipment, special equipment was attracted – a crane with load capacity of 160 tons. The height of the vacuum-evaporated equipment is 24 meters.
At the moment, contractor organization JSC "SMT-41" continues to perform construction works.